Cream stone and wood house with a black entry door, autumn maple and a broad concrete front approach.

Sloan's Lake Park Projects in 2026: What's Changing First

In September, Denver Parks and Recreation closed the parking lot and basketball court near Sheridan Boulevard and 17th Avenue. The building at that intersection is being converted into a maintenance facility. That same month, the mayor stood at the lake and announced a proposed $50 million plan to dredge it.

The dredging got the headlines. Under the city's own schedule, though, nobody starts work in the water before 2028. The work you'll actually walk past this winter and next year is on the rim of the park: the southwest corner, the north courts and the old boathouse. Sloan's Lake is being rebuilt from the edges in, and the lake comes last.

The Water Is on a 2028 Clock

Start with the problem the big project is meant to fix. Decades of sediment have built up on the lakebed. According to the city, many areas now average just 2.5 to 3 feet deep, compared with historical depths of 8 to 12 feet. The sediment contributes to poor water quality and harmful algal blooms, which pull oxygen out of the lake and kill fish. It also leaves the lake less able to handle drought and absorb stormwater.

The city's announcement lays out the proposed funding:

  • Up to $40 million from the St. Anthony Urban Redevelopment Area, created in 2013 to revitalize the Sloan's Lake area
  • $5 million that voters approved for Sloan's Lake in the Vibrant Denver Bond
  • About $5 million from the city's Wastewater Enterprise Fund

The city says the project won't raise taxes or touch the city budget.

Several approvals have to come before any of it. The plan needs votes from the Denver Urban Renewal Authority board and Denver City Council. If both approve, the city expects to issue a contract and finish permitting with the U.S. Army Corps of Engineers in 2027, then start work in 2028. Denverite reported that dredging and the shoreline work are expected to take about 30 months once they begin. A 2028 start and a 30-month build would keep crews working into 2030.

One outlet gave an earlier date. The Denver Post reported on announcement day that construction was estimated to begin in 2027. The city's published schedule, which the Colorado Sun also reported, puts 2027 aside for permitting and 2028 for the start of work.

The Edges Are on a This-Winter Clock

The land-side projects are already in motion, or about to be. Here's the park, corner by corner:

Where in the park Project What's affected Expected timing
Southwest corner, Sheridan Blvd. and 17th Ave. Maintenance yard and shop renovation Parking lot and basketball court closed; a trail segment closes later Closures began September 2026, expected through early 2027
North side North tennis and basketball court replacement Existing north courts Construction starts winter 2026, completion fall 2027
North end Boathouse conversion to community and event space Historic boathouse Construction expected later in 2026; opening forecast in 2028

All three sit on dry ground, and all three have published timelines. The dredging plan is still a proposal.

The Southwest Corner Goes First

If you enter the park from Sheridan, you've probably already lost a parking spot. The Denver Parks project page says the city is renovating the maintenance yard and shop in the park's southwest corner to improve upkeep of parks across northwest Denver. The lot and basketball court near Sheridan and 17th closed in September 2026.

The part to plan around is still ahead. The city says that later in construction, a portion of the trail will close too, and it asks visitors to follow the signed detours. Closures are expected to last through early 2027. If your loop around the lake starts at that corner, expect a detour sometime this winter.

The North Shore Runs Through 2027 and Into 2028

The north side becomes a work zone while the southwest corner is still closed. The north tennis and basketball courts are being replaced, with accessibility improvements. The city's schedule shows design in summer 2025, abatement on the tennis courts in fall 2025, construction starting in winter 2026 and completion in fall 2027. The south playground and tennis courts were replaced earlier and have been finished since October 2023.

The boathouse will change the most. The historic building on the north end currently serves as an operations building. Plans call for a community and event space of about 2,500 to 3,000 square feet, and the city presented the preferred design at a public meeting on January 29, 2026. Denverite reported that the $7 million conversion would include an event room for 171 people, a catering kitchen and a concession stand. Construction was expected later in 2026, with a possible opening in winter 2028.

The city has started lining up food and drink for the building. A Denver Parks request for information covering concessions at Skyline Park and Sloan's Lake anticipated boathouse concession service starting in spring 2028, with a formal proposal process and contract award still to come. No vendor has been named on the city's bidding page.

Why the Land Moves Before the Lake

The order follows the approvals each project needs. Dredging a 177-acre urban lake that draws 2 million visitors a year needs a new funding deal and a federal permit. The city has also said that dredging in a busy park is hard enough that it will treat this project as a test of methods for cleaning other Denver lakes.

Parks director Jolon Clark told Denverite what that means in the near term: "There are still some approvals that need to happen before anything starts to move forward. So in the very short term, not a lot of changes, but the focus throughout the project will be to keep as much of the park open and usable as possible, doing work in the lake." The city says it has already finished smaller fixes, including reshaping parts of the shoreline and installing aerators.

The people with the most riding on the water are pacing themselves too. Denverite reported that the Colorado Dragon Boat Festival has struggled in recent years because the shallow lake makes it hard to find routes for the boats. The festival still returned to the lake on August 29 and 30 this year, according to Westword. Edgewater Mayor Steve Conklin welcomed the announcement, and Denverite noted that Edgewater's commercial areas just west of the park depend on park visitors.

The Sloan's Lake Park Foundation, which turns 10 this year, has pushed for lake investment for five years. Executive director Kurt Weaver told Denverite that the group expects to become more of a "Friends of the Park" organization: "We want to make sure we are out here every week to see what smaller problems are out there. Can we plant some more trees? Do we need more benches? Are the soccer fields upkept?" In other words, the foundation's next role is about the same edges.

The Rim Still Has a Season

None of this closes the park. The paths, the views and the water are still open to the public. Denver's boating rules for city lakes allow hand-launched boats powered by people or wind, ban motorized boats, set boating hours from sunrise to sunset, and warn about low water and muddy conditions.

Closer to the holidays, the Sloan's Lake Holiday BAZAAR returns on Saturday, December 5, from 11 a.m. to 5 p.m. at 1611 N. Raleigh St. Admission is free, and organizers listed 57 confirmed makers as of mid-October.

On the south side, along West Colfax, the Denver Post reports that Jordy's BBQ plans to open in the former Raíces Brewing space at 2060 W. Colfax Ave., targeting early 2027. In early October, Westword reported that the kitchen was still in permitting and buildout, and the owner expected two to three months of construction.

For this winter, plan on a closed lot and a coming trail detour at Sheridan and 17th. North court construction starts this winter and runs through fall 2027, and the boathouse is expected to open in 2028. Work in the lake would start in 2028 at the earliest, under the city's schedule, if the approvals go through.

We follow park projects like these because they shape daily life on the west side long before they show up anywhere else. If you have questions about how the Sloan's Lake work affects your corner of the neighborhood, Eric and Karla are glad to talk it through. Work with The Tack Group.

Work With Us

At The Tack Group, we believe successful real estate begins with genuine connection. As a collaborative husband-and-wife team, we pair deep Denver Metro expertise with a hands-on, detail-driven approach that keeps your needs at the center. From navigating timelines to negotiating with clarity and confidence, we advocate for you at every turn—making your move feel smooth, supported, and stress-free.